“Works have been completed in Shukurbayli substation, integration works are underway, first and second lines to Shusha substation have been installed and are nearing to completion,” said at the next meeting of Working Group on “Energy supply issues” established in the Interdepartmental Center in the video conference format, APA reports.

Noted that works regarding the establishment of power lines, construction of substations in Shusha city have been completed. Works in the substations constructing in Kalbajar, as well as the establishment of power lines from Dashkasan to Kalbajar, continue. Works in the Aghdam substation have started. The establishment of two-circuit power lines between Jabrayil-Gubadli, Gubadli-Zangilan has been launched.

#
#