Construction of TAP completed by 90%

 Construction of TAP completed by 90%
# 17 October 2019 16:36 (UTC +04:00)

89.9% of the work has been completed since the commencement of the Trans-Adriatic Pipeline (TAP) engaged in the transportation of Azerbaijan's gas to Europe. This is an indicator recorded at the end of September, APA-Economics reports citing TAP consortium.

Note that the TAP pipeline, which is part of the Southern Gas Corridor project, is expected to transport 10 billion cubic meters of gas annually to Europe within the Shah Deniz-2 project. This pipeline will run through Greece, Albania and the Adriatic Sea to the south of Italy.

It is expected that Azerbaijani gas will be transported to Europe in 2020.

#
#